PM0011 : Explain the following a. Rolling wave planning b. Decomposition c. Precedence diagramming method d. Dependency determination

Posted on: February 28, 2012

PM0011 : Explain the following

a. Rolling wave planning

b. Decomposition

c. Precedence diagramming method

d. Dependency determination

Answer:-

a. Rolling wave planning :

This is a technique which plans as and when the project unfolds. In this technique the plans are made with the upcoming events

b. Decomposition  :

This technique is about breaking project work packages into smaller more easily manageable units

c. Precedence diagramming method  :

This is a method for constructing project schedule network diagram that has rectangular boxes, depicting nodes and arrows connecting the boxes, depicting the logical relationship between the activities. this technique is also called Activity on Node (AON).

d. Dependency determination :

This technique is used to define the sequence based on the types of dependencies between the activities 

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Author

Learning days (Calendar)

February 2012
M T W T F S S
« Jan   Mar »
 12345
6789101112
13141516171819
20212223242526
272829  

Knowledge Bank (Archives)

I am on Twitter

Error: Twitter did not respond. Please wait a few minutes and refresh this page.

Blog Stats

  • 504,000 hits

Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Join 43 other followers

%d bloggers like this: